Capacitor Bank
Switching
Transients
Shunt capacitor
bank switching transients are often a concern for utility
and industrial engineers that are planning to apply capacitors
at the distribution voltage level (4.16 kV through 34.5 kV).
Their primary area of concern is typically with how the capacitor
switching transients will affect power quality for nearby
industrial and commercial loads.
This
tech-note provides practical background information on capacitor
bank switching transients as well as the transient analysis
capabilities of NEPSI’s consulting engineering group. In addition,
information is provided on how the capacitor bank switching
transients can be reduced or nearly eliminated.
Background
Capacitor banks applied within distribution
substations typically consists of one to four banks of switched
capacitors as shown in Figure 1 (which shows a three step
switched bank). The switched banks are designed to come on
and off automatically based on power factor, vars, and/or
voltage. Due to load variations, a number of switching operations
will occur daily. Each switching event is followed by a low-frequency
decaying ring wave transient that can result in power quality
problems for nearby industrial and commercial loads.

Figure
1 – Typical Utility Substation
Showing a 4.5 MVAR
Capacitor Bank And Adjacent Distribution Loads
Sample
System
To help illustrate capacitor-switching transients,
the system shown in Figure 1 was modeled and simulated with
a transient analysis program. The figure shows a typical distribution
substation with three primary distribution circuits as well
as a three step 4500 kvar automatic capacitor bank. The capacitor
bank is equipped with 0.040 mH transient inrush reactors to
limit the frequency and magnitude of the transient currents
associated with back-to-back capacitor bank switching. (Note:
As will be explained later in this document, the inrush reactors
have an insignificant impact on improving power quality from
switching transients seen by the system. The inrush reactors
are installed to prevent premature vacuum switch failure from
back-to-back capacitor bank switching transients).

Figure
2 – Capacitor Bank Switching
Transient. Bus-2 Phase-to-Phase Voltage
Upon Closing of Phase-A and Phase-B Vacuum Contacts.
Single
Bank Switching Transient
Figure 2 shows the transient that will
occur for the closing of the first 1500 kvar capacitor step
of Figure 1, while no other steps are energized. Due to switch
variations, and possible pre-strike conditions, phase A and
phase B vacuum switches are assumed to close prior to the
phase C switch. For
an ungrounded bank, the first phase switch to close will result
in no current flow or voltage transient. The neutral voltage
will then follow the phase voltage, and phase-to-phase voltage
will be impressed across the remaining two switches. Upon
closure of a second contact, a transient such as the one shown
in Figure 2 will occur. The worse case transient will occur
when the second switch closes near the peak of the phase-to-phase
voltage waveform. Measurements by NEPSI on many capacitor banks at the 15kV level
have indicated that switches will begin to conduct near peak
voltage due to pre-strike.
The
transient of Figure 2 is actually composed of a decaying ring-wave
transient (red curve) superimposed on the voltage waveform
(blue curve) as shown in figure 3. The duration of the decaying
ring-wave transient is dependent on the system X/R ratio at
the capacitor bank. High X/R ratios will result in long durations,
while low X/R ratios will result in short duration transients.
Figure
3 – Low Frequency Decaying Ring
Wave
Resulting From Capacitor Switching
In
examining the transient waveforms shown in figures two, three,
and four, the following statements can be made in regard to
single capacitor bank switching.
- On closing of the second contact (for
an ungrounded bank), the line-to-line system voltage will
be pulled to near zero volts. This is most easily seen in
figure four. This will be referred to as a voltage depression.
- Immediately following the voltage depression,
the system voltage will attempt to recover, but will over-shoot
the normal system voltage by an amount that is nearly equal
to the voltage dip. Theoretically, two per-unit over-voltages
can occur due to capacitor switching.
- The frequency of the capacitor transient
is equal to the system’s natural frequency. Therefore, large
capacitor banks will result in lower frequency decaying
ring wave transients, while small banks will result in higher
frequency ring wave transients.
- The duration of the ring-wave transient
is dependent upon the system X/R ratio at the capacitor
bank. Systems with higher X/R ratios result in longer duration
transients. Transients associated with substation capacitor
banks can last as long as long at 30 to 40 cycles.
Power Quality Concerns
There are three power quality concerns associated
with single capacitor bank switching transients. These concerns
are most easily seen in figure 4, and are as follows:
- The initial voltage depression results
in a loss of voltage of magnitude “D” and duration “T1”.
- The recovering system voltage will result
in an initial transient over-voltage of magnitude “S” and
Duration “T2”.
- Multiple zero-crossings. For the transient
in figure 4, a total of three zero crossings occur before
the natural system voltage zero crossing.
Figure 4 –
Height, Depth, and Time of Voltage Dip and Spike
Shown On Transient Waveform
Power
quality concerns listed as one and two above are most easily
evaluated with the ITI (CBEMA) Curve shown in figure 5. This
curve describes an ac input voltage envelope which typically
can be tolerated (no interruption in function) by most Information
Technology Equipment (ITE) and forms a basis for evaluating
system transients. The curve and its application are for both
steady-stage and transitory conditions and are applicable
to 120-volt nominal system voltages obtained from 120V, 208Y/120V,
and 120/240V 60 Hertz systems. Since the transient voltages
associated with capacitor switching will reflect through a
transformer (by the turns ratio for frequencies up to 3 kHz),
the curves applicability for medium voltage switching transients
and their effects on low voltage equipment is valid.
The
transients associated with switching 1500 kvar, 3000 kvar,
and 4500 kvar are plotted on the CEBEMA curve with colored
diamonds. The diamonds at 0% voltage represent the initial
voltage dip that occur upon closing of the vacuum contacts,
while the diamonds near 200% nominal voltage are for the voltage
over-shoot as the system voltage attempts to stabilize. The
plot of figure 5 shows that the two power quality concerns
are of boarder-line concern. Since the dip and over-voltage
do not actually last as long the duration depicted in Figure
4, power quality problems associated with over-voltage and
under-voltage are only probable for larger banks.
The
CBEMA curve, however, is not suitable for evaluating the power
quality effects of multiple zero-crossings on industrial and
commercial electrical equipment. Equipment that utilizes the
zero-voltage crossing for timing or control is prone to miss-operation.
The transformer connection, capacitor bank size, capacitor
bank connection (grounded or ungrounded), system impedance,
and X/R ratio influence the occurrence of multiple zero crossings.
Even small banks will result in multiple zero crossings.

Figure
5 – ITI (CEBEMA) Curve Showing
Voltage Dip and Spikes
Caused By Various Size Capacitor Banks
Key to Figure
5
Orange
= 1500 kvar Switching Transient
Purple =3000 kvar Switching Transient
Green = 4500 kvar Switching Transient
Back-to-Back Capacitor Bank
Switching Transients
Multiple Capacitor Bank Switching Transients
occur when a capacitor bank is energized in close proximity
to capacitor bank that is already energized. Such a switching
operation is common in multi-step automatic capacitor banks
as shown in figure 1. Upon energization of the uncharged bank,
the adjacent charged bank dumps a high frequency high magnitude
current into the uncharged bank. This high frequency high
magnitude current is limited by the impedance between the
capacitor stages (resistance and reactance of bus work, fuses,
vacuum switches, etc.). Most banks have to be supplemented
with transient inrush reactors to reduce the magnitude of
the transients to within the vacuum switch and fuse ratings.
The high magnitude current is not seen by the power system
as it occurs between the parallel banks.

Figure
6 – Voltage (Red) and Current
(Green) Waveform Associated With
Back-To-Back Capacitor Bank Switching. Current Waveform Is
Current Flowing Into Capacitor Bank Being Energized
In observing
figure 6, the following should be noted in regards to back-to-back
capacitor bank switching:
- The
system voltage still experiences a low frequency decaying
ring wave transient.
- The
voltage depression is not to zero volts, as was the case
for single capacitor bank switching transients.
- The
system voltage over-shoot is reduced to an amount equal
to the voltage depression.
- Multiple
zero-crossings are still possible.
Mitigating Transients Associated With
Capacitor Bank Switching
In purchasing and specifying capacitor banks
and harmonic filter banks, the cost associated with nearby
electrical equipment miss-operation or damage should be evaluated
against the cost of additional equipment to eliminate switching
transients. Capacitor banks and harmonic filter banks in the
2.4kV through 34.5kV voltage range can be equipped with zero
voltage closing controls to nearly eliminate switching transients.
These controls operate their associated vacuum switches so
that contact closure occurs at the zero-voltage crossing point.
Figure
7 shows waveform plots for a capacitor bank switching event
involving the energization of a single 13.8kV 1500 kvar ungrounded-wye
connected capacitor bank. Phase A contacts close at its own
phase-to-ground 0-voltage crossing. At this time, no current
flows because the bank is ungrounded. The capacitor bank neutral
voltage, however, follows the Phase-A voltage (red and blue
curve on top waveform plot). When the phase A voltage or neutral
voltage crosses the Phase-C voltage, Phase-C vacuum switch
closes. At this time Phase-C and Phase-A vacuum switches begin
to conduct current(see bottom set of waveforms).
Phase-B vacuum switch will close when the neutral voltage
(or Phase-A to Phase-C voltage) and phase voltage equal zero.
At this time, all three phases are conducting vars and the
capacitor bank has come on with virtually no voltage transient.
Figure
7 – Simulated Phase-to-Ground
Voltage, Capacitor Bank Neutral Voltage and Vacuum Switch
Current Associated with Zero-Voltage Closing
Key to Figure 7
[BK1A](1)
= Phase A to Ground Voltage at Main Bus
V[BK1B](1) =Phase B to
Ground Voltage at Main Bus
V[BK1C](1) = Phase C to Ground Voltage at Main Bus
V[NEUT1, gnd](1) = Capacitor Bank Neutral to Ground
Voltage
I[BK1C,SW1C](1) = Phase C Vacuum Switch Current
I[BK1B,SW1B](1) = Phase B Vacuum Switch Current
I[BK1A,SW1A](1) = Phase A Vacuum Switch Current
In observing Figure
7, the following key points can be made:
- The
transient over-voltage associated with the energization
of the capacitor bank is negligible.
- The
possibility of multiple zero crossings is eliminated.
- High
inrush currents are eliminated (increasing vacuum switch
life).
Northeast
Power Systems, Inc.
66 Carey Road
Queensbury, New York 12804
Phone: 518-792-4776
Fax: 518-792-5767
E-mail:
sales@nepsi.com
Website
: www.nepsi.com
Copyright © 1999
- 2009 Northeast Power Systems, Inc.
|